Chester supported Apex Water to upgrade Raglan’s wastewater treatment plant, improving performance and increasing capacity for future growth.
Chester supported Apex Water in the delivery of a major upgrade to the Raglan Wastewater Treatment Plant, enhancing treatment performance and improving compliance with wastewater discharge requirements. The project introduced new headworks infrastructure and advanced biological treatment processes, increasing capacity from 3.5MLD to 6MLD to accommodate future growth in Raglan.
Of particular note was the programme scheduling that enabled the bulk earthworks for construction to commence within weeks of project award, while treatment, mechanical and electrical designs progressed in parallel to maintain programme efficiency. During delivery, innovative Membrane Aerated Biofilm Reactor (MABR) technology was incorporated to increase future capacity without the need for additional costly civil works.
Completed ahead of key consent milestones, the upgraded facility provides a resilient, future-focused wastewater solution and is among the first plants in New Zealand to integrate MABR technology, setting a new benchmark for sustainable wastewater treatment infrastructure.
Services Provided by Chester
Awards Received
Recognition Received
Auckland (Head Office)
Level 1, Chester Building
28 The Warehouse Way
Northcote, Auckland 0627
Bay of Plenty
78 Maunganui Road
Mount Maunganui 3116
Northland
Level 2
66 Gillies Street
Kawakawa 0210
Nadi, Fiji
Shop 8 Eden Plaza
Queens Road
Nadi, Fiji